Temporary theatre made of wood

Construction work on the temporary theatre in Unterer Brühl commenced in mid-March. The timber construction in front of the concert hall will provide space for 500 spectators and will be used for around two seasons. Blumer Lehmann is delivering the construction as full-service general contractor.

Named ‘UM!BAU’, the temporary structure will be 50 m long and 26 m wide. The spruce and fir elements are being prefabricated at our plant. A total of 350 m3 of wood will be used. The roof and facades will be clad with section sheet.

The temporary theatre construction is expected to be ready for occupation by mid-September 2020, and will include a stage, orchestra pit, foyer, gallery, storage area and recreation room for artists. The timber construction work will take a total of 14 weeks from mid-April until the end of July 2020.

Click here for the reference

This website uses cookies

We use cookies to personalise content and ads, provide social media features and analyse traffic to our website. We also share information about your use of our website with our social media, advertising and analytics partners. Our partners may combine this information with other data that you have provided to them or that they have collected in the course of your use of the services.